Skip to main content

Belconnen Trunk Sewer upgrade projects

Construction of the Belconnen trunk sewer was completed in early 2024. The new sewer, which was built in public lands parallel to Ginninderra Drive between Copland Drive, Melba and Tillyard Drive, Charnwood will ensure the reliability of the wastewater network is maintained and meets the needs of the growing population of the Belconnen, Gungahlin and Hall communities.

Please see below for key project information and FAQs.

Project overview

The original Belconnen trunk sewer was built in the 1960s and is a critical part of the Belconnen wastewater network which serves Belconnen, Gungahlin and Hall.


Belconnen trunk sewer upgrade project overview


Belconnen trunk sewer pipeline bridge timelapse


Belconnen trunk sewer Evatt OCU mural timelapse

 

The project consisted of:

  • installing approximately ~2.4km of sewer pipe
  • installing 18 sewer manholes and four odour control units
  • installing a 170m long pipe bridge to cross Ginninderra Creek
  • installing four Odour Control Units (OCUs)
  • restoring all impacted areas including the replanting of predominantly native species

The new wastewater pipe has been installed within public lands parallel to Ginninderra Drive between Copland Drive Melba and Tillyard Drive, Charnwood. Please refer to the map below for the pipeline location overview.
In addition to improving capacity, the network also requires extra ventilation and OCUs to protect new and existing sewerage infrastructure and minimise impacts to the surrounding community. See our factsheet on the project need.

Progress to date

The complex project included a number of elements that were completed mainly in 2023.

Activity

Status

Completion date

Sewer pipeline installation

Completed

February 2023 

170-metre Pipe bridge across Ginninderra Creek

Completed

February 2023 

Installation of 18 sewer manholes

Completed

November 2022

Restoration of pipeline corridor and site compound

Completed

October 2023 

North Latham OCU

Completed

October 2023

Latham OCU

Completed

November 2023

Florey OCU

Completed

October 2023

Evatt OCU

Completed

September 2023

Mural artworks for OCU buildings

Completed

December 2023 

Restoration of OCU sites

Completed. As part of our landscaping plans, areas of high environmental sensitivity including Natural Temperate Grasslands (NTG), are being restored and protected. These NTG areas will continue to be monitored and maintained until early 2026.

February 2024


 

Why did we need to upgrade this section of the wastewater network?
Like most of Australia’s capital cities, Canberra’s population is growing and this increases demand on our water and sewer infrastructure. Major development has recently occurred in the Gungahlin region, and planned development at the University of Canberra, the suburb of Lawson, CSIRO's Ginninderra Field Station and an increase in infill development generally, mean that the sewer is nearing capacity and needs to be upgraded to ensure it can continue to meet demand. 

During extreme wet weather events, rainwater and an already steady flow in the wastewater network can result in sewage escaping from the sewer pipes into Ginninderra Creek. Icon Water appreciates how valued the environment and waterways are and these projects will ensure that any risk of overflow into local waterways is significantly reduced.

In addition to the new sewer pipe being installed, the projects will also include four OCUs which will be constructed within public lands in Latham, Florey, Evatt and North Latham.
 

Odour Control Units (OCUs)
Odour Control Units - OCUs are a vital part of the sewer network as they protect the sewer pipes from corrosion and reduce odour through filtration and ventilation. Ventilation using an OCU extends the life of a sewer by reducing the amount of maintenance that the pipeline needs allowing more efficient management of the existing network.

The filters used in the OCU and ventilation stacks absorb gases such as hydrogen sulphide, which is a common source of odour from sewerage systems.

See our factsheet on OCUs.